Sewage Treatment Plant “IDA-Giubiasco” (TI, CH), 2024

Dewatering works for the amplification of the sewage treatment plant “IDA-Giubiasco” (TI, CH)

PURPOSES

The analyze of solutions for lowering groundwater levels in a 28x38m excavation area with a 7m variation. This includes estimating inflows into the excavation pit and proposing alternatives.

 

CLIENT

GEOLOG.CH, 2024.

WHAT WE DID

We enabled realistic and dependable assessment of dewatering needs (pumping rates volumes) to model and cross-compared various scenarios using a working 3D hydrogeological numerical model approach. A solution combining  a pumping system, such as dewatering pumps, at the bottom of the excavation pit and “sheet piles” around the excavation pit has been studied.

Leave a Reply

Your email address will not be published. Required fields are marked *